Showcase

Playground

Alice Springs
Client
ProBuild
Budget
$80,000
Workforce
3
Time Line
1 week

Hardy Landscaping was engaged to prepare earthworks, supply and install playground equipment and softfall flooring.

Our team consisted of 1 supervisor and 2 labourers who coordinated the ordering of project materials, transport and delivery of tools, plant and equipment.  Rental vehicles, accommodation, meals and labour were utilised locally at Alice Springs.  The earthworks were completed after which the equipment and finally the softfall flooring were installed.  No variations or delays were experienced, and the project was delivered to the satisfaction of the client.

Site safety and WHS were diligently applied and the project was completed without any incidents and injury to workers.